Skip to content

Choose which optional content this site may load. You can change this at any time from the Cookie Settings link at the bottom of the page.

Necessary

Remembers your cookie and accessibility choices in your browser. Always on.

Allows audience measurement tools to load, if this site uses them.

Allows content from other services, such as embedded social media posts, to load. These services may set their own cookies.

This site shows ads from Google AdSense. Allowing this lets Google use cookies to show ads based on your interests. Without it, you see non-personalized ads.

Accessibility

Text size 100%

Settings are saved in this browser.

Economy & Consumer

Greece Confirms Survey Permit Request for Power Cable With Planned Israel Link

Greek government spokesperson Pavlos Marinakis confirmed on October 15, 2026, that Nexans had requested permission for survey and cable works on the Greece to Cyprus electricity connection. He said work would begin after the required approval procedures. Israel is part of the wider regional plan, but its proposed connection is a separate segment.

A cable laying ship with a large cable reel on deck at sunrise on the Mediterranean
Cable ship at sunrise · Disclaimer

The development concerns preparatory work for the Great Sea Interconnector, not an operational cable or confirmation that surveying has resumed. According to the Greek government briefing, Nexans submitted the request on behalf of GSI. The surveys are intended to advance the undersea route between Greece and Cyprus within the broader regional project.

Approval Still Comes Before Work

Marinakis said authorization was needed from EXAETH, the Greek committee responsible for the relevant marine research permissions, and the Hellenic Coast Guard. He linked the start of work to completion of the prescribed procedures. Filing the application alone does not establish that those permissions have been issued.

Reuters reported on October 15 that the request sought to allow seabed research to resume. A permit application, an approved permit and a vessel beginning work are separate stages. The announcement establishes the first of those steps rather than a fixed restart date or the completion of surveys.

That distinction matters for a project whose progress depends on administrative decisions as well as engineering. A construction schedule cannot simply be inferred from the date of an application, and commercial operation comes later still.

Two Routes Need to Be Kept Separate

The European Commission describes the Crete to Cyprus section as 898 kilometers long. The broader plan includes an extension to Israel, but that figure is not the length of the Cyprus to Israel cable. The request described by Athens concerns the Greek and Cypriot connection.

In a separate August 13 update, Greek transmission operator IPTO described a proposed link between Kofinou in Cyprus and Hadera in Israel. It put the submarine route at approximately 324 kilometers, with a planned capacity of 1,000 megawatts using 500 kilovolt high voltage direct current technology.

Those are planning specifications for a future connection, not measurements from a cable already transmitting electricity. The route lengths and capacities should not be combined into a claim that the whole regional system is complete.

Where Israel Fits Into the Project

Hadera is the Israeli endpoint in IPTO's published plan. The intended connection would link Israel through Cyprus to the wider system, but progress on the Greek segment alone does not complete the approvals or investment decisions required for the Israeli route.

IPTO's August update reported an investment approval request to the Cypriot and Israeli regulators. It documents a step in that process, rather than establishing the outcome of every subsequent proceeding. The planned 1,000 megawatt capacity is also a measure of power, not annual electricity supply or a promised reduction in household bills.

For Israeli consumers, the project therefore remains a prospective infrastructure connection. Its possible role should be separated from claims about when service will begin or how much any household might save.

Diplomatic Support Is Not a Finished Cable

Reuters described Turkish objections surrounding the maritime area and expressions of US support for moving the project forward. Diplomacy, financing, permits and physical construction remain different parts of the undertaking. Support from one government does not automatically resolve the disputes or provide every authorization required.

Athens's new announcement is narrower and more concrete: an application to put seabed surveying back on an approval and implementation track. Its significance for Israel comes from Cyprus's place in the proposed regional connection. The next step identified by the Greek spokesperson is completion of the permit procedures, not the start of electricity deliveries to Israel.